We’ve made some progress over the past couple weeks (see below), and have updated the project timeline to reflect an end-of-May trend date. This update is based on new information, approvals from the City Code Office, and updated timelines from…
We’ve made some progress over the past couple weeks (see below), and have updated the project timeline to reflect an end-of-May trend date. This update is based on new information, approvals from the City Code Office, and updated timelines from…
As mentioned in the previous update, things slowed a bit over the holiday break. As we’ve also mentioned, we’re expecting our timelines to shift and adjust as we move through the process. At this point, we’re thinking our target date…
NOTE: Correction from previous update … our closing date is Dec 12th, not Dec 15. Progress-To-Date 10/26: Signed a fully-executed contract for the facility 11/6: Roof inspected & it’s in great shape 11/7: Signed a term sheet with Carson Bank…
Progress-To-Date 10/26: Signed a fully-executed contract for the facility 11/6: Roof inspected & it’s in great shape 11/7: Signed a term sheet with Carson Bank for our loan 11/15: Septic inspection & everything is in great shape 11/22: Appraisal completed…