Blog Archives

Live Oaks Facility Update: Week of 1/29/2018

We’ve made some progress over the past couple weeks (see below), and have updated the project timeline to reflect an end-of-May trend date.  This update is based on new information, approvals from the City Code Office, and updated timelines from

Read more ›

Tagged with:

Live Oaks Facility Update: Week of 1/8/2018

As mentioned in the previous update, things slowed a bit over the holiday break.  As we’ve also mentioned, we’re expecting our timelines to shift and adjust as we move through the process.  At this point, we’re thinking our target date

Read more ›

Tagged with:

Live Oaks Facility Update: Week of 12/3/2017 (& a little bit of the week of 12/10 …)

As we’ve mentioned in each update, we are prepared for our schedule to move around from week to week based on new discovery, progress, etc.  With the Thanksgiving & Christmas holidays smack dab in the middle of our design phase,

Read more ›

Tagged with:

Live Oaks Facility Update: Week of 11/26/2017

NOTE: Correction from previous update … our closing date is Dec 12th, not Dec 15. Progress-To-Date 10/26: Signed a fully-executed contract for the facility 11/6: Roof inspected & it’s in great shape 11/7: Signed a term sheet with Carson Bank

Read more ›

Tagged with:

Live Oaks Facility Update: Week of 11/19/2017

Progress-To-Date 10/26: Signed a fully-executed contract for the facility 11/6: Roof inspected & it’s in great shape 11/7: Signed a term sheet with Carson Bank for our loan 11/15: Septic inspection & everything is in great shape 11/22: Appraisal completed

Read more ›

Tagged with:
Archives
Categories